Substation Scout

North Newark

Named in 2 PJM planning documents for 2 projects, from October 17, 2025 to November 14, 2025.

Existingdescribed as
AEPzone
138/69/4 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
North Newark Transformer #1 138/69 kV Replacement
b3968.1
Not printed $6.33 M 06/01/2030 Not printed 2025-11-14
SRRTEP Western
North Newark Transformer #1 138/69 kV Replacement Not printed $6.33 M 06/01/2030 Not printed 2025-10-17
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2025-11-14 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 54
North Newark Transformer #1 138/69 kV Replacement “Replace North Newark TR#1 with a 90 MVA bank.”
138/69/4 kV
2025-10-17 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 49
North Newark Transformer #1 138/69 kV Replacement “Replace North Newark TR#1”
138/69/4 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this