Substation Scout

Linwood

Named in 1 PJM planning document for 1 project, on April 7, 2026.

Not stateddescribed as
PECOzone
230kVkV as printed
1mentions

PJM interconnection queue

A PJM queue substation page has the same name: Linwood (PA) — 3 queue requests filed, 3 active.

Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Navy Yard-Richmond New 230kV Line
PE-2025-008
Engineering Not printed Phase 1 – 12/31/2029, Phase 2 – 6/1/2031 500 MW 2026-04-07
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-04-07 TEAC
Item 08 - PECO Supplemental Projects p. 16
Navy Yard-Richmond New 230kV Line No role wording
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this