Named in 4 PJM planning documents for 3 projects, from April 15, 2026 to August 4, 2026.

Existingdescribed as
ATSIzone
345 kV, 69 kVkV as printed
4mentions

Also printed as: Chamberlin Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
ATSI Transmission Zone M-3 Process Chamberlin 69 kV Breakers
ATSI-2023-028 · s3374.1
Engineering $4.20M 12/31/2024 Not printed 2026-09-08*
SRRTEP Western
Aurora-Chamberlin No. 1 69 kV Line
ATSI-2026-025
Not printed Not printed Not printed 120 MWs 2026-04-15
SRRTEP Western
Chamberlin-Harding 345 kV S-21 Line
ATSI-2026-048
Conceptual $0.91M 12/11/2026 Not printed 2026-08-04
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2024 RTEP p. 108
ATSI Transmission Zone M-3 Process Chamberlin 69 kV Breakers “At Chamberlin Substation, replace 69 kV circuit breakers B-31, B-39 and B-74”
69 kV
2026-08-04 TEAC
Item 04 - ATSI Supplemental Projects p. 6
Chamberlin-Harding 345 kV S-21 Line “At Chamberlin Station, replace one circuit breaker, disconnect switches, and substation conductor.”
345 kV
2026-07-07 TEAC
Item 05 - ATSI Supplemental Projects p. 3
Chamberlin-Harding 345 kV S-21 Line No role wording
345 kV
2026-04-15 SRRTEP Western
Item 03 - ATSI Supplemental Project p. 3
Aurora-Chamberlin No. 1 69 kV Line No role wording
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.