Miami

Named in 4 PJM planning documents for 3 projects, from October 8, 2024 to January 17, 2025.

Existingdescribed as
AMPTzone
138/69kVkV as printed
4mentions

Also printed as: Miami sub · Miami Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Miami Transformer
b3918.1
Not printed $12M 6/30/2028 Not printed 2025-01-17
SRRTEP Western
Miami Transformer Not printed $12M 6/30/2028 Not printed 2024-12-13
SRRTEP Western
Tipp City, OH
AMPT-2023-003 & Dayton-2023-004 · s3351.1 (AMPT); s3351.2 (AES)
Not printed $39.6M 6/30/2028 40MW 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AMPT local plan submission of the supplemental projects for 2024 RTEP p. 16
Tipp City, OH “Add one additional breaker, a 2nd 138/69kV transformer, replace five 69kV breakers & four 138kV breakers.”
138/69kV
2025-01-17 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 4
Miami Transformer “replace five 69kV breakers & four 138kV breakers at the Miami substation”
2024-12-13 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 5
Miami Transformer “replace five 69kV breakers & four 138kV breakers at the Miami substation.”
2024-10-08 TEAC
Informational Only - AMPT Local Plan submission of supplemental project 2024 p. 16
Tipp City, OH “Rebuild 2.0 miles of the existing 6692 line from AES Ohio Miami sub”