Substation Scout

Court

Named in 2 PJM planning documents for 2 projects, from February 12, 2026 to July 17, 2026.

Not stateddescribed as
ACEzone
69 kV, 69kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
ACE Transmission Zone: b3227
b3227
Not printed $20M 6/1/2026 Not printed 2026-02-12
SRRTEP Mid-Atlantic
Court 69kV Substation
ACE-2026-003
Not printed Not printed Not printed Not printed 2026-07-17
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$13.2 M → $20M 2026-02-12 2026-02-12

Every mention

DateDocumentProjectWhat the document says about it
2026-07-17 SRRTEP Mid-Atlantic
Item 05 - ACE Supplemental Projects p. 3
Court 69kV Substation “The Court T1 69/12kV distribution transformer has no high-side interrupting device”
69kV
2026-02-12 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 6
ACE Transmission Zone: b3227 No role wording
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.