Substation Scout

E Monument

Named in 1 PJM planning document for 1 project, on November 13, 2026.

Work described at itdescribed as
AMPTzone
138 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Danville area reinforcement
AMPT 2026-008
Engineering $30.553 M 01/31/2030 Not printed 2026-11-13
SRRTEP Western

Other substations in this project

“Danville area reinforcement” also names 4 other substations, with what the most recent document says about each.

Every mention

DateDocumentProjectWhat the document says about it
2026-11-13 SRRTEP Western
Item 03 - AMPT Supplemental Projects Presentation p. 9
Danville area reinforcement “Upgrade relay equipment at Danville, E Danville, and E Monument. Install new 138 kV breaker at E Monument to bring the sub and protection up to modern standards”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.