Endor

Named in 1 PJM planning document for 1 project, on November 13, 2026.

Newdescribed as
AEPzone
138kVkV as printed
1mentions

Described as new. The quoted wording calls this substation new. “Construct a greenfield five breaker ring bus station” — source, page 13

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Endor Station
AEP-2025-OH010
Not printed $54.887 M 01/01/2029 135 MW 2026-11-13
SRRTEP Western

Other substations in this project

“Endor Station” also names 6 other substations, with what the most recent document says about each.

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named GOOD HOPE SW; LEMASTER; LOCKBOURNE → CIRCLEVILLE; ENDOR; GOOD HOPE; HARRISON; LEMASTER; LOCKBOURNE 2025-10-17 2026-11-13

Every mention

DateDocumentProjectWhat the document says about it
2026-11-13 SRRTEP Western
Item 02 - AEP Supplemental Projects Presentation p. 13
Endor Station “Construct a greenfield five breaker ring bus station”
138kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first