Substation Scout

Norse

Named in 1 PJM planning document for 1 project, on December 1, 2026.

Newdescribed as
AEPzone
345kVkV as printed
1mentions

Described as new. The quoted wording calls this substation new. “Build greenfield 345kV breaker and half substation” — source, page 33

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Northwest Ohio 345kV Customer Delivery Points & System Reinforcements
AEP-2024-IM014, AEP-2025-OH016, AEP-2025-OH017, AEP-2025-OH018, AEP-2025-OH019
Conceptual $607.548 M 09/26/2031 1,300 MW 2026-12-01
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named ALLEN; EAST LIMA; RP MONE; SORENSON → BOSC 1A 1B CUSTOMER; BOSC 2A 2B CUSTOMER; EAST LIMA; EBERSOLE; FLAG CITY; FOSTORIA CENTRAL; HILLCREST; LYKA; MADDOX CREEK; NORSE; NORTH FINDLAY; PALMER 1 2 CUSTOMER; PEONY 1 2 CUSTOMER; PYRITE; SAIDIN; SORENSON; VALOR 1 2 CUSTOMER; WAYNE TRACE; WAYNEDALE 2024-11-06 2026-12-01

Every mention

DateDocumentProjectWhat the document says about it
2026-12-01 TEAC
Item 03 - AEP Supplemental Projects - Presentation p. 33
Northwest Ohio 345kV Customer Delivery Points & System Reinforcements “Build greenfield 345kV breaker and half substation”
345kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.