Good Hope Switch
Named in 1 PJM planning document for 1 project, on November 13, 2026.
Work described at itdescribed as
AEPzone
138kVkV as printed
1mentions
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Endor Station AEP-2025-OH010 |
Not printed | $54.887 M | 01/01/2029 | 135 MW | 2026-11-13 SRRTEP Western |
Other substations in this project
“Endor Station” also names 6 other substations, with what the most recent document says about each.
- Circleville AEP Not stated
- Endor AEP New — “Construct a greenfield five breaker ring bus station” (p. 13)
- Good Hope SW AEP Not stated
- Harrison AEP, OH Work described at it — “Add one 138kV circuit breaker at the existing Harrison station” (p. 13)
- Lemaster AEP Not stated
- Lockbourne AEP Not stated
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Substations named | GOOD HOPE SW; LEMASTER; LOCKBOURNE → CIRCLEVILLE; ENDOR; GOOD HOPE; HARRISON; LEMASTER; LOCKBOURNE | 2025-10-17 | 2026-11-13 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-11-13 | SRRTEP Western Item 02 - AEP Supplemental Projects Presentation p. 13 |
Endor Station | “the existing
Good Hope Switch - Harrison 138kV single circuit line will be rebuilt” 138kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation", or when a PJM document prints a rename for the same project (src/ingest/rtepAliases.json; the entry lists its old names).
- role is "new" only where a cited document phrase calls the substation new, describes constructing it, or calls it proposed (graded by src/lib/roleBasis.js), "existing" where a phrase describes work at it, otherwise "unknown".
- expansion is set on a substation that is not "new" where a cited phrase describes a new voltage level, a new or expanded yard, bus or bay, or a named load connected to it (graded by src/lib/expansionBasis.js). It reproduces what the document describes and adds nothing to it.
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.