Substation Scout

Good Hope Switch

Named in 1 PJM planning document for 1 project, on November 13, 2026.

Work described at itdescribed as
AEPzone
138kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Endor Station
AEP-2025-OH010
Not printed $54.887 M 01/01/2029 135 MW 2026-11-13
SRRTEP Western

Other substations in this project

“Endor Station” also names 6 other substations, with what the most recent document says about each.

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named GOOD HOPE SW; LEMASTER; LOCKBOURNE → CIRCLEVILLE; ENDOR; GOOD HOPE; HARRISON; LEMASTER; LOCKBOURNE 2025-10-17 2026-11-13

Every mention

DateDocumentProjectWhat the document says about it
2026-11-13 SRRTEP Western
Item 02 - AEP Supplemental Projects Presentation p. 13
Endor Station “the existing Good Hope Switch - Harrison 138kV single circuit line will be rebuilt”
138kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first