North Boyertown

Named in 3 PJM planning documents for 3 projects, from December 12, 2024 to October 6, 2026.

Existingdescribed as
METEDzone
230 kV, 69 kVkV as printed
3mentions

Also printed as: North Boyertown Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Hosensack Substation
ME-2024-006
Conceptual $39.36 M 12/31/2030 Not printed 2026-10-06
TEAC
North Boyertown Substation
ME-2024-024
Not printed Not printed Not printed Not printed 2024-12-12
SRRTEP Mid-Atlantic
Carsonia - Lyons - North Boyertown 69 kV 75 Line: Customer Connection, PA
ME-2026-008
Not printed Not printed 10/31/2028 approximately 13 MW 2026-08-13
SRRTEP Mid-Atlantic

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 09 - MetEd Supplemental Projects - Presentation p. 4
Hosensack Substation “At North Boyertown Substation: Revise relay settings”
230 kV
2026-08-13 SRRTEP Mid-Atlantic
Item 03 - MetEd Supplemental Projects p. 3
Carsonia - Lyons - North Boyertown 69 kV 75 Line: Customer Connection, PA No role wording
69 kV
2024-12-12 SRRTEP Mid-Atlantic
Item 09 - MetEd Supplemental Projects p. 3
North Boyertown Substation “A faulted 69 kV bus tie breaker at North Boyertown Substation”
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.