Substation Scout

East Flemington

Named in 5 PJM planning documents for 5 projects, from October 8, 2024 to August 4, 2026.

Existingdescribed as
JCPLzone
230 kV, 230-34.5 kV, 34.5 kV, 34.5 kVkV as printed
10mentions

Also printed as: East Flemington Substation

PJM interconnection queue

A PJM queue substation page has the same name: East Flemington (NJ) — 3 queue requests filed, 1 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Automatic Restoration Projects
JCPL-2023-023 · s3401.1
Not printed $ 0.64 M 12/31/2025 Not printed 2024-10-08
TEAC
East Flemington Substation
JCPL-2023-051 · s3274.1
Engineering $13.95M 09/29/2031 Not printed 2026-08-04
TEAC
East Flemington Substation
JCPL-2023-052 · s3275.1
Engineering $13.95M 12/29/2028 Not printed 2026-08-04
TEAC
East Flemington Substation
JCPL-2024-051
Not printed Not printed Not printed 31 MW 2024-12-03
TEAC
East Flemington Substation, NJ
JCPL-2026-005
Not printed Not printed Not printed Not printed 2026-02-12
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $13.95M → $7.18M 2026-08-04 Not reported
Cost estimate $7.18M → $13.95M 2024-10-08 2026-08-04
In-service date 09/29/2031 → 12/31/2026 2026-08-04 Not reported
In-service date 12/31/2026 → 09/29/2031 2024-10-08 2026-08-04
Cost estimate $13.95M → $7.18M 2026-08-04 Not reported
Cost estimate $7.18M → $13.95M 2024-10-08 2026-08-04
In-service date 12/29/2028 → 12/31/2027 2026-08-04 Not reported
In-service date 12/31/2027 → 12/29/2028 2024-10-08 2026-08-04

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 47
East Flemington Substation “Replace the 230-34.5 kV No. 3 Transformer at East Flemington Substation”
230-34.5 kV
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 49
East Flemington Substation “Replace the 230-34.5 kV No. 4 Transformer at East Flemington Substation”
230-34.5 kV
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 83
Automatic Restoration Projects “At East Flemington Substation, replace relaying”
34.5 kV
2026-08-04 TEAC
Item 05 - JCPL Supplemental Projects p. 10
East Flemington Substation “Replace the 230-34.5 kV No. 4 Transformer at East Flemington Substation with a 90 MVA unit.”
230-34.5 kV
2026-08-04 TEAC
Item 05 - JCPL Supplemental Projects p. 8
East Flemington Substation “Replace the 230-34.5 kV No. 3 Transformer at East Flemington Substation with a 90 MVA unit.”
230-34.5 kV
2026-02-12 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 4
East Flemington Substation, NJ “relaying at East Flemington Substation are more than 45 years old and are approaching end of life.”
34.5 kV
2024-12-03 TEAC
Item 05 - JCPL Supplemental Projects p. 3
East Flemington Substation “East Flemington Substation currently contains obsolete 230 kV equipment”
230 kV
2024-10-08 TEAC
Informational Only - JCPL Local Plan submission of supplemental project 2024 p. 47
East Flemington Substation “Replace the 230-34.5 kV No. 3 Transformer at East Flemington Substation”
2024-10-08 TEAC
Informational Only - JCPL Local Plan submission of supplemental project 2024 p. 49
East Flemington Substation “Replace the 230-34.5 kV No. 4 Transformer at East Flemington Substation”
2024-10-08 TEAC
Informational Only - JCPL Local Plan submission of supplemental project 2024 p. 83
Automatic Restoration Projects “At East Flemington Substation, replace relaying”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this