Vienna

Named in 2 PJM planning documents for 2 projects, from October 16, 2025 to November 13, 2025.

Existingdescribed as
DPLzone
138kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Vienna – Loretto 138kV Line
b4023.1
Not printed 1.814 M 5/31/2030 Not printed 2025-11-13
SRRTEP Mid-Atlantic
Vienna – Loretto 138kV Line Not printed 1.814 M 5/31/2030 Not printed 2025-10-16
SRRTEP Mid-Atlantic

Every mention

DateDocumentProjectWhat the document says about it
2025-11-13 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 3
Vienna – Loretto 138kV Line “Upgrade existing 500 & 750 SDCU on Vienna side of Vienna - Loretto facility”
2025-10-16 SRRTEP Mid-Atlantic
Item 02 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 3
Vienna – Loretto 138kV Line “Upgrade existing 500 & 750 SDCU on Vienna side of Vienna - Loretto facility”
138kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.