Substation Scout

Tower

Named in 2 PJM planning documents for 2 projects, on October 8, 2024.

Existingdescribed as
AMPTzone
69kVkV as printed
4mentions

Also printed as: Tower 69kV Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Tipp City, OH
AMPT-2023-002 · s3217.1 (AMPT)
Not printed $1.24M 6/1/2025 10MW 2024-10-08
TEAC
Tipp City, OH
AMPT-2023-003 & Dayton-2023-004 · s3351.1 (AMPT); s3351.2 (AES)
Not printed $39.6M 6/30/2028 40MW 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AMPT local plan submission of the supplemental projects for 2024 RTEP p. 16
Tipp City, OH “Install new line relays and CCVT’s for line Tower – Canal line terminal.”
69kV
2026-09-08* SRRTEP Western
AMPT local plan submission of the supplemental projects for 2024 RTEP p. 6
Tipp City, OH “Perform necessary work to terminate new 69 kV line to Tower station”
69kV
2024-10-08 TEAC
Informational Only - AMPT Local Plan submission of supplemental project 2024 p. 16
Tipp City, OH “Install new line relays and CCVT’s for line Tower – Canal line terminal”
69kV
2024-10-08 TEAC
Informational Only - AMPT Local Plan submission of supplemental project 2024 p. 6
Tipp City, OH “Install new line relays, RTU, and CCVT’s for the new 69kV line terminal”
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this