Glassboro

Named in 1 PJM planning document for 1 project, on March 18, 2026.

Existingdescribed as
ACEzone
69kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
ACE-2026-002 Not printed Not printed Not printed Not printed 2026-03-18
SRRTEP Mid-Atlantic

Every mention

DateDocumentProjectWhat the document says about it
2026-03-18 SRRTEP Mid-Atlantic
Item 02 - ACE Supplemental Projects p. 3
ACE-2026-002 “Inspections of the Glassboro 69kV substation identified the electromechanical relays are in poor condition and need to be replaced.”
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.