Stuart

Named in 2 PJM planning documents for 1 project, from February 3, 2026 to July 7, 2026.

Existingdescribed as
DAYTONzone
345 kVkV as printed
2mentions

Also printed as: Stuart Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dayton Transmission Zone M-3 Process
Dayton-2026-001
Conceptual $51.7M 11/01/2028 1300 MW 2026-07-07
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-07-07 TEAC
item 11 - Dayton Supplemental Projects p. 8
Dayton Transmission Zone M-3 Process “Expand Stuart Substation to accommodate the new 345 kV feeds”
345 kV
2026-02-03 TEAC
Item 06 - Dayton Supplemental Projects p. 4
Dayton Transmission Zone M-3 Process No role wording