Manor Woods

Named in 1 PJM planning document for 1 project, on February 3, 2026.

Not stateddescribed as
APSzone
230 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Doubs - Lime Kiln 230 kV Line
APS-2025-021
Conceptual $63.16 M 09/23/2032 Not printed 2026-02-03
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate 36.75 → $63.16 M 2025-11-04 2026-02-03
In-service date 09/2030 → 02/18/2032 2025-09-09 2025-11-04
In-service date 02/18/2032 → 09/23/2032 2025-11-04 2026-02-03
Substations named DOUBS; LIME KILN → DOUBS; LIME KILN; QUANTUM 300; SAGE 2025-09-09 2025-11-04
Substations named DOUBS; LIME KILN; QUANTUM 300; SAGE → DOUBS; LIME KILN; MANOR WOODS; QUANTUM 300; SAGE 2025-11-04 2026-02-03

Every mention

DateDocumentProjectWhat the document says about it
2026-02-03 TEAC
Item 04 - APS Supplemental Projects p. 4
Doubs - Lime Kiln 230 kV Line No role wording
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.