Warren
Named in 11 PJM planning documents for 6 projects, from October 8, 2024 to October 6, 2026.
Existingdescribed as
PENELECzone
115 kV, 115kV, 230 kVkV as printed
13mentions
Also printed as: Warren Substation
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Warren 115kV Breaker “NO.1 XFMR” Replacement b3988.1 |
Cancelled | $0.957M | Not printed | Not printed | 2026-02-12 SRRTEP Mid-Atlantic |
| Warren – Falconer 115 kV Line: New Customer s3291.1 |
Engineering | $8.45M | 04/28/2028 | Not printed | 2025-05-15 SRRTEP Mid-Atlantic |
| Warren 115kV Breaker “NO.1 XFMR” Replacement | Not printed | $0.957M | 6/1/2030 | Not printed | 2025-10-16 SRRTEP Mid-Atlantic |
| Erie South Substation PN-2020-005 and PN-2023-018 |
Not printed | Not printed | Not printed | Not printed | 2024-10-08 TEAC |
| Warren – Falconer 115 kV Line – New Customer PN-2023-007 · s3291.1 |
Not printed | $8.45M | 04/28/2028 | Not printed | 2026-10-06 TEAC |
| Glade Substation PN-2024-013 · s3631.1 |
Not printed | $12 M | 12/17/2027 | Not printed | 2025-10-08 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate prior value printed on the same page |
$1.5M → $8.45M | 2025-05-15 | 2025-05-15 |
| Cost estimate prior value printed on the same page |
$1.5M → $8.45M | Not reported | Not reported |
| Cost estimate | $1.5M → $8.45M | Not reported | Not reported |
| Cost estimate | $8.45M → $1.5M | 2026-10-06 | Not reported |
| Cost estimate prior value printed on the same page |
$1.5M → $8.45M | 2026-10-06 | 2026-10-06 |
| Cost estimate | $1.5M → $8.45M | 2024-10-08 | 2026-10-06 |
| In-service date | 04/28/2027 → 04/28/2028 | Not reported | Not reported |
| In-service date | 04/28/2028 → 04/28/2027 | 2026-10-06 | Not reported |
| In-service date | 04/28/2027 → 04/28/2028 | 2024-10-08 | 2026-10-06 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Informational Only - Penelec Local Plan Submission of Supplemental Projects for 2026 p. 7 |
Warren – Falconer 115 kV Line – New Customer | “Adjust relay settings at Warren Substation” 115 kV |
| 2026-10-01* | SRRTEP Mid-Atlantic Penelec local plan submission for 2026 RTEP p. 7 |
Warren – Falconer 115 kV Line – New Customer | “Adjust relay settings at Warren Substation” |
| 2026-09-08* | SRRTEP Mid-Atlantic Penelec local plan submission for 2025 RTEP p. 16 |
Glade Substation | “At Warren Substation, on the Glade line terminal:
▪ Replace substation conductor.
▪ Install new relaying and control equipment.” 230 kV |
| 2026-09-08* | SRRTEP Mid-Atlantic Penelec local plan submission for 2024 RTEP p. 15 |
Warren – Falconer 115 kV Line – New Customer | “Adjust relay settings at Warren Substation” |
| 2026-09-08* | SRRTEP Mid-Atlantic Penelec local plan submission for 2024 RTEP p. 37 |
Erie South Substation | No role wording 230 kV |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 3 |
Warren 115kV Breaker “NO.1 XFMR” Replacement | “Replace the over dutied Warren 115 kV circuit breakers” 115 kV |
| 2025-11-13 | SRRTEP Mid-Atlantic Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 40 |
Warren 115kV Breaker “NO.1 XFMR” Replacement | “Replace the over dutied Warren 115 kV circuit breakers” 115 kV |
| 2025-10-16 | SRRTEP Mid-Atlantic Item 02 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 40 |
Warren 115kV Breaker “NO.1 XFMR” Replacement | “Replace the over dutied Warren 115 kV circuit breakers” 115kV |
| 2025-10-08 | TEAC Informational Only - Penelec Local Plan Submission of the Supplemental Projects for 2025 p. 16 |
Glade Substation | “At Warren Substation, on the Glade line terminal: § Replace substation conductor.” |
| 2025-05-15 | SRRTEP Mid-Atlantic Item 02 - Penelec Supplemental Projects p. 3 |
Warren – Falconer 115 kV Line: New Customer | “Adjust relay settings at Warren Substation” 115 kV |
| 2025-03-04 | TEAC Item 07 - Penelec Supplemental Projects p. 4 |
Glade Substation | “At Warren Substation, on the Glade line terminal: -Replace substation conductor” |
| 2024-10-08 | TEAC Informational Only - PENELEC Local Plan submission of supplemental project 2024 p. 15 |
Warren – Falconer 115 kV Line – New Customer | “Adjust relay settings at Warren Substation” 115 kV |
| 2024-10-08 | TEAC Informational Only - PENELEC Local Plan submission of supplemental project 2024 p. 37 |
Erie South Substation | No role wording 230 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.