Kendall County E. C.

Named in 2 PJM planning documents for 2 projects, from February 3, 2026 to March 10, 2026.

Existingdescribed as
COMEDzone
345kVkV as printed
2mentions

Also printed as: Kendall County E.C.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Customer in Morris
ComEd-2025-011
Conceptual $99M 6/1/2028 1,000 MW 2026-02-03
TEAC
Customer in Minooka
ComEd-2025-015
Conceptual $41.5M 7/1/2027 588 MW 2026-03-10
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-03-10 TEAC
Item 08 - ComEd Supplemental Projects p. 5
Customer in Minooka “existing ring bus configuration at Kendall County E. C.”
345kV
2026-02-03 TEAC
Item 10 - ComEd Supplemental Projects p. 9
Customer in Morris No role wording
345kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.