Quantum 300 Substation
Named in 3 PJM planning documents for 2 projects, from November 4, 2025 to September 8, 2026.
Newdescribed as
APSzone
230 kVkV as printed
3mentions
Described as new: “Construct new Quantum 300 Substation” — source, page 4
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Doubs - Lime Kiln 230 kV Line APS-2025-021 |
Conceptual | $63.16 M | 09/23/2032 | Not printed | 2026-02-03 TEAC |
| New Customer Connection APS-2026-039 |
Conceptual | $8.02M | 04/12/2032 | 368 MW | 2026-09-08 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate | 36.75 → $63.16 M | 2025-11-04 | 2026-02-03 |
| In-service date | 09/2030 → 02/18/2032 | 2025-09-09 | 2025-11-04 |
| In-service date | 02/18/2032 → 09/23/2032 | 2025-11-04 | 2026-02-03 |
| Substations named | DOUBS; LIME KILN → DOUBS; LIME KILN; QUANTUM 300; SAGE | 2025-09-09 | 2025-11-04 |
| Substations named | DOUBS; LIME KILN; QUANTUM 300; SAGE → DOUBS; LIME KILN; MANOR WOODS; QUANTUM 300; SAGE | 2025-11-04 | 2026-02-03 |
| In-service date | 4/30/2032 → 04/12/2032 | 2026-07-07 | 2026-09-08 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08 | TEAC Item 05 - APS Supplemental Projects p. 7 |
New Customer Connection | “Install four 230 kV breakers at the Quantum 300 Substation constructed per APS-2025-021” 230 kV |
| 2026-02-03 | TEAC Item 04 - APS Supplemental Projects p. 4 |
Doubs - Lime Kiln 230 kV Line | “Construct new Quantum 300 Substation” |
| 2025-11-04 | TEAC Item 04 - APS Supplemental Projects - Version 7 p. 12 |
Doubs - Lime Kiln 230 kV Line | “Construct new Quantum 300 Substation” 230 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.