Substation Scout

Lock

Named in 2 PJM planning documents for 1 project, from November 4, 2025 to February 3, 2026.

Existingdescribed as
PECOzone
230 kVkV as printed
2mentions

PJM interconnection queue

A PJM queue substation page has the same name: Lock (PA) — 2 queue requests filed, 0 active.

Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Lock Substation New 230 kV Breaker
PE-2025-006
Engineering $2.4 million 12/31/2026 Not printed 2026-02-03
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-02-03 TEAC
Item 08 - PECO Supplemental Projects p. 4
Lock Substation New 230 kV Breaker “Install a new 230 kV 4000A circuit breaker on the Lock 230 kV ring bus”
230 kV
2025-11-04 TEAC
Item 09 - PECO Supplemental Projects p. 3
Lock Substation New 230 kV Breaker “expansion of existing distribution substations”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this