Tributary

Named in 4 PJM planning documents for 2 projects, from June 5, 2025 to October 6, 2026.

Newdescribed as
DOMzone
230 kVkV as printed
4mentions

Described as new: “Construct Tributary 230 kV switching station” — source, page 7

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental Tributary 230kV Delivery - REC
DOM-2024-0009 · s3721
Engineering $32.3M 04/01/2027 108 MW 2025-10-08
TEAC
Emy 230kV Delivery - REC
DOM-2025-0051 · s4029
Conceptual $26M 05/01/2030 212 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named EMY → EMY; KRAKEN; NEW POST; TRIBUTARY 2025-11-04 2026-02-03

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 75
Emy 230kV Delivery - REC No role wording
2026-02-03 TEAC
Item 12 - DOM Supplemental Projects p. 8
Emy 230kV Delivery - REC No role wording
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 64
Dominion Transmission Zone: Supplemental Tributary 230kV Delivery - REC “Construct Tributary 230 kV switching station”
230 kV
2025-06-05 TEAC
Item 08 - DOM Supplemental Projects p. 7
Dominion Transmission Zone: Supplemental Tributary 230kV Delivery - REC “Construct Tributary 230 kV switching station”
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.