Poe
Named in 2 PJM planning documents for 2 projects, from December 12, 2024 to February 3, 2026.
Existingdescribed as
DOMzone
115kV, 230kVkV as printed
2mentions
Also printed as: Poe Substation
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Line #23 Bell Ave to Suffolk 115 kV Partial Rebuild B3759 |
Not printed | $41M | 6/1/2027 | Not printed | 2024-12-12 SRRTEP Southern |
| James Hill 230kV Delivery - DEV DOM-2024-0036 |
Conceptual | $26M | 12/30/2031 | in excess of 100 MW | 2026-02-03 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate prior value printed on the same page |
$23.5M → $41M | 2024-12-12 | 2024-12-12 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-02-03 | TEAC Item 12 - DOM Supplemental Projects p. 6 |
James Hill 230kV Delivery - DEV | “ring bus at Poe (b4000.334-.336) and there
is no room for further expansion to accommodate additional line terminals” 230kV |
| 2024-12-12 | SRRTEP Southern Item 01 - SRRTEP South - Reliability Analysis Update p. 3 |
Line #23 Bell Ave to Suffolk 115 kV Partial Rebuild | No role wording 115kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.