Named in 5 PJM planning documents for 2 projects, from February 12, 2026 to October 6, 2026.

Existingdescribed as
PPLzone
230kV, 69kVkV as printed
5mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Cumberland - West Shore 1 & 2 69kV line upgrades
PPL-2026-0009
Conceptual $20.3 M 06/30/2029 Not printed 2026-10-06
TEAC
Bressler 230kV Switchyard
PPL-2026-0037
Conceptual $169 M 03/31/2029 900 MW 2026-09-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named CUMBERLAND; WEST SHORE → CUMBERLAND; WERTZVILLE; WEST SHORE 2026-02-12 2026-03-18
In-service date 03/2029 → 03/31/2029 2026-06-02 2026-09-08

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 88
Cumberland - West Shore 1 & 2 69kV line upgrades No role wording
69kV
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 88
Cumberland - West Shore 1 & 2 69kV line upgrades No role wording
69kV
2026-09-08 TEAC
Item 07 - PPL Supplemental Projects p. 9
Bressler 230kV Switchyard “Install three 230kV line terminals with three new 230kV breakers”
230kV
2026-03-18 SRRTEP Mid-Atlantic
Item 09 - PPL Supplemental Projects p. 15
Cumberland - West Shore 1 & 2 69kV line upgrades No role wording
69kV
2026-02-12 SRRTEP Mid-Atlantic
Item 05 - PPL Supplemental Projects p. 3
Cumberland - West Shore 1 & 2 69kV line upgrades No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.