Clinton

Named in 4 PJM planning documents for 4 projects, from October 16, 2025 to October 6, 2026.

Not stateddescribed as
PPLzone
69kVkV as printed
9mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Kenmar, PA
PPL-2019-0006
Conceptual $30 M 12/31/2028 Not printed 2026-10-06
TEAC
Hughesville, PA
PPL-2025-0021
Conceptual Not printed 01/30/2028 Not printed 2026-10-06
TEAC
Watson, PA
PPL-2026-0005
Conceptual $0.5 M 04/01/2027 Not printed 2026-10-06
TEAC
Fairfield, PA
PPL-2026-0008
Conceptual $0.2 M 10/08/2028 Not printed 2026-02-12
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named LYCOMING; MUNCY → CLINTON; LYCOMING; MUNCY 2025-07-17 2025-10-16
Substations named HUGHESVILLE → CLINTON; HUGHESVILLE; MUNCY 2025-12-11 2026-10-06
Substations named WATSON → CLINTON; MILTON; WATSON 2026-01-15 2026-02-12
Substations named FAIRFIELD; LYCOMING; MUNCY TIE → FAIRFIELD; LYCOMING; MUNCY 2026-10-06 Not reported
Substations named FAIRFIELD → CLINTON; FAIRFIELD; LYCOMING 2026-01-15 2026-02-12
Substations named CLINTON; FAIRFIELD; LYCOMING → FAIRFIELD; LYCOMING; MUNCY TIE 2026-02-12 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 11
Kenmar, PA No role wording
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 29
Watson, PA No role wording
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 35
Hughesville, PA No role wording
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 11
Kenmar, PA No role wording
69kV
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 29
Watson, PA No role wording
69kV
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 35
Hughesville, PA No role wording
69kV
2026-02-12 SRRTEP Mid-Atlantic
Item 05 - PPL Supplemental Projects p. 20
Watson, PA “Clinton 69kV Substation”
69kV
2026-02-12 SRRTEP Mid-Atlantic
Item 05 - PPL Supplemental Projects p. 24
Fairfield, PA “Clinton 69kV Substation”
69kV
2025-10-16 SRRTEP Mid-Atlantic
Item 06 - PPL Supplemental Projects p. 6
Kenmar, PA No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.