Substation Scout

Byron

Named in 1 PJM planning document for 1 project, on February 3, 2026.

Not stateddescribed as
COMEDzone
345kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Customer in Rockford
ComEd-2025-014
Conceptual $92M 1/1/2028 600 MW 2026-02-03
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-02-03 TEAC
Item 10 - ComEd Supplemental Projects p. 13
Customer in Rockford No role wording
345kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.