Mudd Tavern

Named in 3 PJM planning documents for 1 project, from October 8, 2025 to October 6, 2026.

Newdescribed as
DOMzone
230 kV, 230kVkV as printed
3mentions

Described as new: “new substation (Mudd Tavern)” — source, page 3

Also printed as: Mudd Tavern Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2025-0032 · s3991
Conceptual $ 22 M 3/1/2029 300 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $ 26M → $ 22 M 2026-02-03 2026-10-06
In-service date 8/1/2029 → 03/01/2029 2025-10-08 2026-02-03
Status conceptual (Conceptual) → conceptual (Planning) 2026-02-03 2026-10-06
Substations named MUDD TAVERN → MUDD TAVERN; ORROCK MATTA 2025-10-08 2026-02-03

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 53
Dominion Transmission Zone: Supplemental Customer Load Request “new substation (Mudd Tavern)”
230 kV
2026-02-03 TEAC
Item 12 - DOM Supplemental Projects p. 3
Dominion Transmission Zone: Supplemental Customer Load Request “new substation (Mudd Tavern)”
230kV
2025-10-08 TEAC
Item 12 - DOM Supplemental Projects p. 3
Dominion Transmission Zone: Supplemental Customer Load Request “new substation (Mudd Tavern)”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this