Substation Scout

Parsons

Named in 5 PJM planning documents for 1 project, from October 8, 2024 to October 6, 2026.

Existingdescribed as
AEPzone
138 kVkV as printed
5mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone: Supplemental s3440.3 Scope Change
AEP-2022-OH071 · s3440.3
Conceptual $77.4M 06/05/2027 675 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$57.5M → $77.4M Not reported Not reported
Cost estimate $57.5M → $77.4M Not reported Not reported
Cost estimate $77.4M → $57.5M 2026-10-06 Not reported
Cost estimate
prior value printed on the same page
$57.5M → $77.4M 2026-02-13 2026-02-13
Cost estimate $57.5M → $77.4M 2024-10-08 2026-02-13
Cost estimate
prior value printed on the same page
$57.5M → $77.4M 2026-10-06 2026-10-06
Substations named BEATTY; BIXBY; CANAL; CLINTON; CYPRUS; MARION; MOUND; OBETZ; PARSONS; ROZELLE; SAINT CLAIR AVENUE; WAVERLY → BEATTY; BIXBY; CYPRUS; MARION; PARSONS; SAINT CLAIR AVENUE; WAVERLY Not reported Not reported
Substations named BEATTY; BIXBY; CANAL; CYPRUS; MARION; PARSONS; WAVERLY → BEATTY; BIXBY; CANAL; CLINTON; CYPRUS; MARION; MOUND; OBETZ; PARSONS; ROZELLE; SAINT CLAIR AVENUE; WAVERLY 2026-10-06 Not reported
Substations named BEATTY; BIXBY; CANAL; CLINTON; CYPRUS; MARION; MOUND; OBETZ; PARSONS; ROZELLE; SAINT CLAIR AVENUE; WAVERLY → BEATTY; BIXBY; CLINTON; CYPRUS; MARION; MOUND; OBETZ; PARSONS; ROZELLE; SAINT CLAIR AVENUE; WAVERLY 2024-10-08 2026-02-13
Substations named BEATTY; BIXBY; CLINTON; CYPRUS; MARION; MOUND; OBETZ; PARSONS; ROZELLE; SAINT CLAIR AVENUE; WAVERLY → BEATTY; BIXBY; CANAL; CYPRUS; MARION; PARSONS; WAVERLY 2026-02-13 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 51
AEP Transmission Zone: Supplemental s3440.3 Scope Change “Install (1) 69.1 MVAR cap bank”
138 kV
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 51
AEP Transmission Zone: Supplemental s3440.3 Scope Change “Install (1) 69.1 MVAR cap bank”
138 kV
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 108
AEP Transmission Zone: Supplemental s3440.3 Scope Change “Install (1) 69.1 MVAR cap bank to resolve N-1-1 voltage issues”
138 kV
2026-02-13 SRRTEP Western
Item 02 - AEP Supplemental Projects p. 3
AEP Transmission Zone: Supplemental s3440.3 Scope Change “Parsons 138 kV: Install (1) 69.1 MVAR cap bank”
138 kV
2024-10-08 TEAC
Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 108
AEP Transmission Zone: Supplemental s3440.3 Scope Change “Install (1) 69.1 MVAR cap bank”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this