Emy

Named in 3 PJM planning documents for 1 project, from November 4, 2025 to October 6, 2026.

Newdescribed as
DOMzone
230kVkV as printed
3mentions

Described as new: “new substation (Emy)” — source, page 7

Also printed as: Emy Sub

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2025-0051 · s4029
Conceptual $26M 05/01/2030 212 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named EMY → EMY; KRAKEN; NEW POST; TRIBUTARY 2025-11-04 2026-02-03

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 74
Dominion Transmission Zone: Supplemental Customer Load Request “new substation (Emy)”
230kV
2026-02-03 TEAC
Item 12 - DOM Supplemental Projects p. 7
Dominion Transmission Zone: Supplemental Customer Load Request “new substation (Emy)”
230kV
2025-11-04 TEAC
Item 13 - DOM Supplemental Projects p. 8
Dominion Transmission Zone: Supplemental Customer Load Request “new substation (Emy)”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.