Waugh Chapel
Named in 7 PJM planning documents for 7 projects, from October 8, 2024 to February 3, 2026.
PJM interconnection queue
A PJM queue substation page has the same name: Waugh Chapel (MD) — 5 queue requests filed, 1 active.
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| BGE-2023-015 | Engineering | $0.7M | 10/17/2024 | Not printed | 2024-10-08 TEAC |
| BGE-2023-016 | Engineering | $0.7M | 6/6/2024 | Not printed | 2024-10-08 TEAC |
| Waugh Chapel Circuit Breaker B4 BGE-2024-002 · s3560.1 |
Under construction | $0.7M | 4/10/2025 | Not printed | 2025-10-08 TEAC |
| Waugh Chapel Circuit Breaker B7 BGE-2024-003 · s3561.1 |
Engineering | $0.7M | 10/9/2025 | Not printed | 2025-10-08 TEAC |
| Waugh Chapel Circuit Breaker B10 BGE-2024-004 · s3562.1 |
Engineering | $0.7M | 5/15/2025 | Not printed | 2025-10-08 TEAC |
| Waugh Chapel Circuit Breaker B12 BGE-2024-005 · s3563.1 |
Engineering | $0.7M | 11/13/2025 | Not printed | 2025-10-08 TEAC |
| Customer in Calvert County BGE-2025-011 |
Engineering | $263.5M | 3/1/2028 | 880 MW | 2026-02-03 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Status | engineering (Engineering) → under-construction (Construction) | 2025-02-13 | 2025-10-08 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08* | SRRTEP Mid-Atlantic BGE local plan submission for 2024 RTEP p. 12 |
BGE-2023-015 | “Replace Waugh Chapel circuit breaker B6” 115kV |
| 2026-09-08* | SRRTEP Mid-Atlantic BGE local plan submission for 2024 RTEP p. 14 |
BGE-2023-016 | “Replace Waugh Chapel circuit breaker B9” 115kV |
| 2026-09-08* | SRRTEP Mid-Atlantic BGE local plan submission for 2025 RTEP p. 2 |
Waugh Chapel Circuit Breaker B4 | “Replace Waugh Chapel circuit breaker B4” 115kV |
| 2026-09-08* | SRRTEP Mid-Atlantic BGE local plan submission for 2025 RTEP p. 4 |
Waugh Chapel Circuit Breaker B7 | “Replace Waugh Chapel circuit breaker B7” 115kV |
| 2026-09-08* | SRRTEP Mid-Atlantic BGE local plan submission for 2025 RTEP p. 6 |
Waugh Chapel Circuit Breaker B10 | “Replace Waugh Chapel circuit breaker B10” 115kV |
| 2026-09-08* | SRRTEP Mid-Atlantic BGE local plan submission for 2025 RTEP p. 8 |
Waugh Chapel Circuit Breaker B12 | “Replace Waugh Chapel circuit breaker B12” 115kV |
| 2026-02-03 | TEAC Item 09 - BGE Supplemental Projects p. 4 |
Customer in Calvert County | “Cut into existing 500kV Calvert Cliffs to Waugh Chapel” 500kV |
| 2025-10-08 | TEAC Informational Only - BGE Local Plan Submission of the Supplemental Projects for 2025 p. 2 |
Waugh Chapel Circuit Breaker B4 | “Replace Waugh Chapel circuit breaker B4” 115kV |
| 2025-10-08 | TEAC Informational Only - BGE Local Plan Submission of the Supplemental Projects for 2025 p. 4 |
Waugh Chapel Circuit Breaker B7 | “Replace Waugh Chapel circuit breaker B7” 115kV |
| 2025-10-08 | TEAC Informational Only - BGE Local Plan Submission of the Supplemental Projects for 2025 p. 6 |
Waugh Chapel Circuit Breaker B10 | “Replace Waugh Chapel circuit breaker B10” 115kV |
| 2025-10-08 | TEAC Informational Only - BGE Local Plan Submission of the Supplemental Projects for 2025 p. 8 |
Waugh Chapel Circuit Breaker B12 | “Replace Waugh Chapel circuit breaker B12” 115kV |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 05 - BGE Supplemental Projects p. 3 |
Waugh Chapel Circuit Breaker B4 | “Replace Waugh Chapel circuit breaker B4” 115kV |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 05 - BGE Supplemental Projects p. 5 |
Waugh Chapel Circuit Breaker B7 | “Replace Waugh Chapel circuit breaker B7” 115kV |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 05 - BGE Supplemental Projects p. 7 |
Waugh Chapel Circuit Breaker B10 | “Replace Waugh Chapel circuit breaker B10” 115kV |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 05 - BGE Supplemental Projects p. 9 |
Waugh Chapel Circuit Breaker B12 | “Replace Waugh Chapel circuit breaker B12” 115kV |
| 2024-12-12 | SRRTEP Mid-Atlantic Item 11 - BGE Supplemental Projects p. 3 |
Waugh Chapel Circuit Breaker B4 | “Waugh Chapel 115kV circuit breaker #B4 installed in 1996 is in deteriorating condition” 115kV |
| 2024-12-12 | SRRTEP Mid-Atlantic Item 11 - BGE Supplemental Projects p. 4 |
Waugh Chapel Circuit Breaker B7 | “Waugh Chapel 115kV circuit breaker #B7 installed in 1996 is in deteriorating condition” 115kV |
| 2024-12-12 | SRRTEP Mid-Atlantic Item 11 - BGE Supplemental Projects p. 5 |
Waugh Chapel Circuit Breaker B10 | “Waugh Chapel 115kV circuit breaker #B10 installed in 1996 is in deteriorating condition” 115kV |
| 2024-12-12 | SRRTEP Mid-Atlantic Item 11 - BGE Supplemental Projects p. 6 |
Waugh Chapel Circuit Breaker B12 | “Waugh Chapel 115kV circuit breaker #B12 installed in 1996 is in deteriorating condition” 115kV |
| 2024-10-08 | TEAC Informational Only - BGE Local Plan submission of supplemental project 2024 p. 12 |
BGE-2023-015 | “Replace Waugh Chapel circuit breaker B6” 115kV |
| 2024-10-08 | TEAC Informational Only - BGE Local Plan submission of supplemental project 2024 p. 14 |
BGE-2023-016 | “Replace Waugh Chapel circuit breaker B9” 115kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.