Substation Scout

Waugh Chapel

Named in 7 PJM planning documents for 7 projects, from October 8, 2024 to February 3, 2026.

Existingdescribed as
BGEzone
115kV, 500kVkV as printed
21mentions

PJM interconnection queue

A PJM queue substation page has the same name: Waugh Chapel (MD) — 5 queue requests filed, 1 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
BGE-2023-015 Engineering $0.7M 10/17/2024 Not printed 2024-10-08
TEAC
BGE-2023-016 Engineering $0.7M 6/6/2024 Not printed 2024-10-08
TEAC
Waugh Chapel Circuit Breaker B4
BGE-2024-002 · s3560.1
Under construction $0.7M 4/10/2025 Not printed 2025-10-08
TEAC
Waugh Chapel Circuit Breaker B7
BGE-2024-003 · s3561.1
Engineering $0.7M 10/9/2025 Not printed 2025-10-08
TEAC
Waugh Chapel Circuit Breaker B10
BGE-2024-004 · s3562.1
Engineering $0.7M 5/15/2025 Not printed 2025-10-08
TEAC
Waugh Chapel Circuit Breaker B12
BGE-2024-005 · s3563.1
Engineering $0.7M 11/13/2025 Not printed 2025-10-08
TEAC
Customer in Calvert County
BGE-2025-011
Engineering $263.5M 3/1/2028 880 MW 2026-02-03
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Status engineering (Engineering) → under-construction (Construction) 2025-02-13 2025-10-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
BGE local plan submission for 2024 RTEP p. 12
BGE-2023-015 “Replace Waugh Chapel circuit breaker B6”
115kV
2026-09-08* SRRTEP Mid-Atlantic
BGE local plan submission for 2024 RTEP p. 14
BGE-2023-016 “Replace Waugh Chapel circuit breaker B9”
115kV
2026-09-08* SRRTEP Mid-Atlantic
BGE local plan submission for 2025 RTEP p. 2
Waugh Chapel Circuit Breaker B4 “Replace Waugh Chapel circuit breaker B4”
115kV
2026-09-08* SRRTEP Mid-Atlantic
BGE local plan submission for 2025 RTEP p. 4
Waugh Chapel Circuit Breaker B7 “Replace Waugh Chapel circuit breaker B7”
115kV
2026-09-08* SRRTEP Mid-Atlantic
BGE local plan submission for 2025 RTEP p. 6
Waugh Chapel Circuit Breaker B10 “Replace Waugh Chapel circuit breaker B10”
115kV
2026-09-08* SRRTEP Mid-Atlantic
BGE local plan submission for 2025 RTEP p. 8
Waugh Chapel Circuit Breaker B12 “Replace Waugh Chapel circuit breaker B12”
115kV
2026-02-03 TEAC
Item 09 - BGE Supplemental Projects p. 4
Customer in Calvert County “Cut into existing 500kV Calvert Cliffs to Waugh Chapel”
500kV
2025-10-08 TEAC
Informational Only - BGE Local Plan Submission of the Supplemental Projects for 2025 p. 2
Waugh Chapel Circuit Breaker B4 “Replace Waugh Chapel circuit breaker B4”
115kV
2025-10-08 TEAC
Informational Only - BGE Local Plan Submission of the Supplemental Projects for 2025 p. 4
Waugh Chapel Circuit Breaker B7 “Replace Waugh Chapel circuit breaker B7”
115kV
2025-10-08 TEAC
Informational Only - BGE Local Plan Submission of the Supplemental Projects for 2025 p. 6
Waugh Chapel Circuit Breaker B10 “Replace Waugh Chapel circuit breaker B10”
115kV
2025-10-08 TEAC
Informational Only - BGE Local Plan Submission of the Supplemental Projects for 2025 p. 8
Waugh Chapel Circuit Breaker B12 “Replace Waugh Chapel circuit breaker B12”
115kV
2025-02-13 SRRTEP Mid-Atlantic
Item 05 - BGE Supplemental Projects p. 3
Waugh Chapel Circuit Breaker B4 “Replace Waugh Chapel circuit breaker B4”
115kV
2025-02-13 SRRTEP Mid-Atlantic
Item 05 - BGE Supplemental Projects p. 5
Waugh Chapel Circuit Breaker B7 “Replace Waugh Chapel circuit breaker B7”
115kV
2025-02-13 SRRTEP Mid-Atlantic
Item 05 - BGE Supplemental Projects p. 7
Waugh Chapel Circuit Breaker B10 “Replace Waugh Chapel circuit breaker B10”
115kV
2025-02-13 SRRTEP Mid-Atlantic
Item 05 - BGE Supplemental Projects p. 9
Waugh Chapel Circuit Breaker B12 “Replace Waugh Chapel circuit breaker B12”
115kV
2024-12-12 SRRTEP Mid-Atlantic
Item 11 - BGE Supplemental Projects p. 3
Waugh Chapel Circuit Breaker B4 “Waugh Chapel 115kV circuit breaker #B4 installed in 1996 is in deteriorating condition”
115kV
2024-12-12 SRRTEP Mid-Atlantic
Item 11 - BGE Supplemental Projects p. 4
Waugh Chapel Circuit Breaker B7 “Waugh Chapel 115kV circuit breaker #B7 installed in 1996 is in deteriorating condition”
115kV
2024-12-12 SRRTEP Mid-Atlantic
Item 11 - BGE Supplemental Projects p. 5
Waugh Chapel Circuit Breaker B10 “Waugh Chapel 115kV circuit breaker #B10 installed in 1996 is in deteriorating condition”
115kV
2024-12-12 SRRTEP Mid-Atlantic
Item 11 - BGE Supplemental Projects p. 6
Waugh Chapel Circuit Breaker B12 “Waugh Chapel 115kV circuit breaker #B12 installed in 1996 is in deteriorating condition”
115kV
2024-10-08 TEAC
Informational Only - BGE Local Plan submission of supplemental project 2024 p. 12
BGE-2023-015 “Replace Waugh Chapel circuit breaker B6”
115kV
2024-10-08 TEAC
Informational Only - BGE Local Plan submission of supplemental project 2024 p. 14
BGE-2023-016 “Replace Waugh Chapel circuit breaker B9”
115kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this