Substation Scout

Sage

Named in 10 PJM planning documents for 6 projects, from October 8, 2024 to October 6, 2026.

Existingdescribed as
APSzone
230 kVkV as printed
14mentions

Also printed as: Sage Substation · Sage 230 kV Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Sage 230 kV Customer Load Increase
APS-2023-017 · s3152.1
Not printed $1.5M 10/01/2025 576 MW 2024-10-08
TEAC
Doubs – Sage 230 kV New Customer
APS-2023-029 · s3150.2
Not printed $23.2M 12/31/2025 approximately 300 MW 2025-10-08
TEAC
Doubs - Lime Kiln 230 kV Line
APS-2025-021
Conceptual $63.16 M 09/23/2032 Not printed 2026-02-03
TEAC
New Customer Connection
APS-2026-039
Conceptual $8.02M 04/12/2032 368 MW 2026-09-08
TEAC
New Customer Connection
APS-2026-041
Conceptual $54.99M 11/08/2032 1000 MW 2026-09-08
TEAC
New Customer Connection
APS-2026-044
Conceptual $5 M 09/14/2031 165 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $23.2M → $20.8M 2025-10-08 Not reported
Cost estimate $20.8M → $8M Not reported Not reported
Cost estimate
prior value printed on the same page
$20.8M → 23.2M 2025-01-07 2025-01-07
Cost estimate $20.8M → 23.2M 2024-10-08 2025-01-07
In-service date 12/31/2025 → 09/01/2025 2025-10-08 Not reported
In-service date 09/01/2025 → 12/31/2027 Not reported Not reported
In-service date 09/01/2025 → 12/31/2025 2024-10-08 2025-01-07
Substations named DOUBS; LIME KILN; QUANTUM 400; SAGE → DOUBS; QUANTUM 400; SAGE Not reported Not reported
Cost estimate 36.75 → $63.16 M 2025-11-04 2026-02-03
In-service date 09/2030 → 02/18/2032 2025-09-09 2025-11-04
In-service date 02/18/2032 → 09/23/2032 2025-11-04 2026-02-03
Substations named DOUBS; LIME KILN → DOUBS; LIME KILN; QUANTUM 300; SAGE 2025-09-09 2025-11-04
Substations named DOUBS; LIME KILN; QUANTUM 300; SAGE → DOUBS; LIME KILN; MANOR WOODS; QUANTUM 300; SAGE 2025-11-04 2026-02-03
In-service date 4/30/2032 → 04/12/2032 2026-07-07 2026-09-08
In-service date 12/31/2032 → 11/08/2032 2026-07-07 2026-09-08

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 07 - APS Supplemental Projects - Presentation p. 13
New Customer Connection “Install two 230 kV breakers, extend 230 kV line to wholesale Customer station”
230 kV
2026-09-08 TEAC
Item 05 - APS Supplemental Projects p. 3
New Customer Connection No role wording
230 kV
2026-09-08 TEAC
Item 05 - APS Supplemental Projects p. 6
New Customer Connection No role wording
230 kV
2026-09-08 TEAC
Item 05 - APS Supplemental Projects p. 9
New Customer Connection “Install two new 230 kV breakers at Sage Substation”
230 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 3
Sage 230 kV Customer Load Increase “Expand the existing 3-breaker ring bus into a 6 breaker, breaker-and-a-half substation”
230 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 7
Doubs – Sage 230 kV New Customer “Modify line relay settings at Doubs and Sage substations”
230 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2025 RTEP p. 18
Doubs – Sage 230 kV New Customer “Modify line relay settings at Doubs and Sage substations”
230 kV
2026-07-07 TEAC
Item 06 - APS Supplemental Projects p. 4
New Customer Connection No role wording
230 kV
2026-02-03 TEAC
Item 04 - APS Supplemental Projects p. 4
Doubs - Lime Kiln 230 kV Line “between the new breaker-and-a-half substation and Sage Substation”
2025-11-04 TEAC
Item 04 - APS Supplemental Projects - Version 7 p. 12
Doubs - Lime Kiln 230 kV Line No role wording
230 kV
2025-10-08 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2025 p. 18
Doubs – Sage 230 kV New Customer “Modify line relay settings at Doubs and Sage substations”
230 kV
2025-01-07 TEAC
Item 05 - APS Supplemental Project p. 8
Doubs – Sage 230 kV New Customer “Modify line relay settings at Doubs and Sage substations”
230 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 3
Sage 230 kV Customer Load Increase “Expand the existing 3-breaker ring bus into a 6 breaker, breaker-and-a-half substation”
230 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 6
Doubs – Sage 230 kV New Customer “Modify line relay settings at Doubs and Sage substations”
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this