Substation Scout

Yeat

Named in 4 PJM planning documents for 5 projects, from December 3, 2024 to August 4, 2026.

Newdescribed as
PJM system-widezone
500kV, 765/500/230kVkV as printed
6mentions

Described as new: “Build a new 765/500/230kV Yeat substation” — source, page 77

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Recommended Solution: 2024-W1-967
b4000.344
Not printed $704.33 M 6/1/2029 Not printed 2025-01-07
TEAC
2024W1 – Regional Cluster Recommended Solution: 2024-W1-820
b4000.355
Not printed $978.76 M 6/1/2029 Not printed 2026-08-04
TEAC
Yeat Substation Relocation Update
b4000.357
Not printed Not printed Not printed Not printed 2026-02-03
TEAC
2024W1 – Regional Cluster Preferred Solution: 2024-W1-820
2024-W1-820
Not printed $1,055.3 M 6/1/2029 Not printed 2024-12-03
TEAC
2024W1 – Regional Cluster Preferred Solution: 2024-W1-967
2024-W1-967
Not printed $704.25 M 6/1/2029 Not printed 2024-12-03
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$704.25 M → $704.33 M 2025-01-07 2025-01-07
Cost estimate
prior value printed on the same page
$571.63M → $661.63M 2026-05-08 2026-05-08
Cost estimate $704.33 M → $661.63M 2025-01-07 2026-05-08
In-service date 6/1/2029 → 9/16/2030 2025-01-07 2026-05-08
Substations named ELMONT; KRAKEN; LADYSMITH; NORTH ANNA; POSSUM POINT; YEAT → AQUIA HARBOR; BRISTERS; KRAKEN; LADYSMITH; NORTH ANNA; STAFFORD; THORNBURG 2025-01-07 2026-05-08
Cost estimate
prior value printed on the same page
$1,055.3 M → $1,109.89M 2025-01-07 2025-01-07
Cost estimate
prior value printed on the same page
$1,109.89M → $978.76 M 2026-08-04 2026-08-04
Cost estimate $1,109.89M → $978.76 M 2026-05-08 2026-08-04
Substations named BRISTERS; ELK RUN; JOSHUA FALLS; MEADOWBROOK; VINT HILL; YEAT → BRISTERS; CULPEPER YEAT; CUNNINGHAM; ELK RUN; ELMONT; JOSHUA FALLS; KRAKEN; MEADOWBROOK; MIDLOTHIAN; MORRISVILLE; MOSBY; NOKESVILLE; NORTH ANNA; POSSUM PT; SPOTSYLVANIA; VINT HILL; VONTAY; WISHING STAR; YEAT 2025-01-07 2026-04-07
Substations named BRISTERS; CULPEPER YEAT; CUNNINGHAM; ELK RUN; ELMONT; JOSHUA FALLS; KRAKEN; MEADOWBROOK; MIDLOTHIAN; MORRISVILLE; MOSBY; NOKESVILLE; NORTH ANNA; POSSUM PT; SPOTSYLVANIA; VINT HILL; VONTAY; WISHING STAR; YEAT → ANDERSON BRANCH; BRISTERS; CULPEPER YEAT; ELK RUN; ELMONT; JOSHUA FALLS; KRAKEN; MEADOWBROOK; MORRISVILLE; MOSBY; NOKESVILLE; POSSUM PT; SPOTSYLVANIA; VINT HILL; VONTAY; WISHING STAR; YEAT 2026-04-07 2026-05-08
Substations named ANDERSON BRANCH; BRISTERS; CULPEPER YEAT; ELK RUN; ELMONT; JOSHUA FALLS; KRAKEN; MEADOWBROOK; MORRISVILLE; MOSBY; NOKESVILLE; POSSUM PT; SPOTSYLVANIA; VINT HILL; VONTAY; WISHING STAR; YEAT → BRISTERS; CLOVERDALE; ELK RUN; JOSHUA FALLS; MEADOWBROOK; VINT HILL; YEAT 2026-05-08 2026-08-04

Every mention

DateDocumentProjectWhat the document says about it
2026-08-04 TEAC
Item 13 - Reliability Analysis Update p. 32
2024W1 – Regional Cluster Recommended Solution: 2024-W1-820 “Build a new 765/500/230kV substation called Yeat”
765/500/230kV
2026-02-03 TEAC
Item 13 - Reliability Analysis Update p. 8
Yeat Substation Relocation Update “Build a new 765/500/230kV substation called Yeat”
765/500/230kV
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 59
Recommended Solution: 2024-W1-967 “new substaiton called Yeat”
500kV
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 61
2024W1 – Regional Cluster Recommended Solution: 2024-W1-820 “Build a new 765/500/230kV substation called Yeat”
765/500/230kV
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 76
2024W1 – Regional Cluster Preferred Solution: 2024-W1-967 “Tie in 500kV line Kraken into Yeat substation”
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 77
2024W1 – Regional Cluster Preferred Solution: 2024-W1-820 “Build a new 765/500/230kV Yeat substation”
765/500/230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this