Substation Scout

Elwood

Named in 1 PJM planning document for 1 project, on February 3, 2026.

Not stateddescribed as
COMEDzone
345kVkV as printed
1mentions

PJM interconnection queue

A PJM queue substation page has the same name: Elwood (IL) — 4 queue requests filed, 3 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Customer in Joliet
ComEd-2025-016
Conceptual $269M 7/1/2028 1,800 MW 2026-02-03
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-02-03 TEAC
Item 10 - ComEd Supplemental Projects p. 15
Customer in Joliet No role wording
345kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this