Berks

Named in 5 PJM planning documents for 2 projects, from February 12, 2026 to October 6, 2026.

Not stateddescribed as
PPLzone
69kVkV as printed
5mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
PPL-2023-0014 Conceptual $0.9M 11/30/2025 Not printed 2026-09-08*
SRRTEP Mid-Atlantic
Berks - South Akron 2 69kV upgrade
PPL-2026-0010
Conceptual $38.3 M 12/31/2028 Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 90
Berks - South Akron 2 69kV upgrade No role wording
69kV
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 90
Berks - South Akron 2 69kV upgrade No role wording
69kV
2026-09-08* SRRTEP Mid-Atlantic
PPL local plan submission for 2024 RTEP p. 19
PPL-2023-0014 No role wording
69kV
2026-03-18 SRRTEP Mid-Atlantic
Item 09 - PPL Supplemental Projects p. 17
Berks - South Akron 2 69kV upgrade No role wording
69kV
2026-02-12 SRRTEP Mid-Atlantic
Item 05 - PPL Supplemental Projects p. 4
Berks - South Akron 2 69kV upgrade No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.