Batesville
Named in 4 PJM planning documents for 2 projects, from March 4, 2025 to October 6, 2026.
Existingdescribed as
AEPzone
345kVkV as printed
6mentions
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| MISO Tranche 2 Projects AEP-2024-IM018 · s3608.1-7 |
Conceptual | $0M (PJM) | 2032-2034 | Not printed | 2026-10-06 TEAC |
| Hanna, IN/Tanners Creek, IN AEP-2025-IM010 · s3956.1 |
Conceptual | $520 M | 10/15/2031 | Not printed | 2026-10-06 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate | $173M → $0M (PJM) | 2025-03-04 | 2026-10-06 |
| In-service date | 06/01/2032 → 2032-2034 | 2024-12-03 | 2025-03-04 |
| Substations named | BABCOCK; DRESSER; FAIRBANKS; GREEN ACRES; GREENTOWN; GWYNNEVILLE; HANNA; JEFFERSON; LULU; OLIVE; ROCKPORT; SORENSON; SULLIVAN; TANNERS CREEK; UNIVERSITY PARK → BABCOCK; BATESVILLE; DRESSER; FAIRBANKS; FALL CREEK; GREEN ACRES; GREENTOWN; GWYNNEVILLE; HANNA; JEFFERSON; LULU; MADISON COUNTY; OLIVE; PIKE COUNTY; ROCKPORT; SORENSON; SULLIVAN; SUNNYSIDE; TANNERS CREEK; UNIVERSITY PARK | 2024-12-03 | 2025-03-04 |
| Substations named | BABCOCK; BATESVILLE; DRESSER; FAIRBANKS; FALL CREEK; GREEN ACRES; GREENTOWN; GWYNNEVILLE; HANNA; JEFFERSON; LULU; MADISON COUNTY; OLIVE; PIKE COUNTY; ROCKPORT; SORENSON; SULLIVAN; SUNNYSIDE; TANNERS CREEK; UNIVERSITY PARK → BABCOCK; BATESVILLE; GWYNNEVILLE; MADISON COUNTY; PIKE COUNTY; SORENSON; SULLIVAN | 2025-03-04 | 2026-10-06 |
| Substations named | BATESVILLE; GWYNNEVILLE; HANNA; JUNCTION TOWER; TANNERS CREEK → BATESVILLE; GWYNNEVILLE; HANNA; TANNERS CREEK | 2026-10-06 | Not reported |
| Substations named | HANNA; JUNCTION TOWER; SUNNYSIDE; TANNERS CREEK → BATESVILLE; GWYNNEVILLE; HANNA; JUNCTION TOWER; SUNNYSIDE; TANNERS CREEK | 2025-11-04 | 2026-06-02 |
| Substations named | BATESVILLE; GWYNNEVILLE; HANNA; JUNCTION TOWER; SUNNYSIDE; TANNERS CREEK → BATESVILLE; GWYNNEVILLE; HANNA; JUNCTION TOWER; TANNERS CREEK | 2026-06-02 | 2026-10-06 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-07* | SRRTEP Western AEP local plan submission of the supplemental projects for 2026 RTEP p. 6 |
MISO Tranche 2 Projects | “existing station Batesville” 345kV |
| 2026-10-07* | SRRTEP Western AEP local plan submission of the supplemental projects for 2026 RTEP p. 74 |
Hanna, IN/Tanners Creek, IN | “loop Duke stations Gwynneville and Batesville to Tanners Creek - Hanna 345 kV line” |
| 2026-10-06 | TEAC Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 6 |
MISO Tranche 2 Projects | “existing station Batesville to cut in” |
| 2026-10-06 | TEAC Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 74 |
Hanna, IN/Tanners Creek, IN | No role wording |
| 2026-06-02 | TEAC Item 06 - AEP Supplemental Projects p. 7 |
Hanna, IN/Tanners Creek, IN | No role wording |
| 2025-03-04 | TEAC Item 08 - AEP Supplemental Projects p. 4 |
MISO Tranche 2 Projects | “existing station Batesville to cut in” |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.