Substation Scout

Dutch Fork

Named in 5 PJM planning documents for 2 projects, from December 13, 2024 to October 6, 2026.

Existingdescribed as
APSzone
138 kVkV as printed
7mentions

Also printed as: Dutch Fork Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dutch Fork – Enon 138 kV Line
APS-2023-033 · s3930.1
Not printed $41.70M 12/08/2029 Not printed 2026-10-06
TEAC
New Customer Connection
APS-2024-110 · s3755.1
Conceptual $5.8 M 08/14/2026 20 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 1/15/2026 → 08/14/2026 2024-12-13 2025-04-11

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 3
New Customer Connection “Adjust relay settings at Dutch Fork and Windsor substations”
138 kV
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 69
Dutch Fork – Enon 138 kV Line “At Dutch Fork Substation: Remove wave trap, replace circuit breaker, disconnect switches, substation conductor and relaying.”
138 kV
2026-09-28* SRRTEP Western
APS local plan submission of the supplemental projects for 2026 RTEP p. 3
New Customer Connection “Adjust relay settings at Dutch Fork and Windsor substations”
2026-09-28* SRRTEP Western
APS local plan submission of the supplemental projects for 2026 RTEP p. 69
Dutch Fork – Enon 138 kV Line “At Dutch Fork Substation: Remove wave trap”
2026-06-17 SRRTEP Western
Item 03 - APS Supplemental Projects p. 18
Dutch Fork – Enon 138 kV Line “At Dutch Fork Substation: Remove wave trap, replace circuit breaker”
138 kV
2025-04-11 SRRTEP Western
Item 06 - APS Supplemental Project p. 13
New Customer Connection “Adjust relay settings at Dutch Fork and Windsor substations”
138 kV
2024-12-13 SRRTEP Western
Item 15 - APS Supplemental Project p. 3
New Customer Connection No role wording
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.