Garman

Named in 4 PJM planning documents for 2 projects, from September 18, 2025 to October 6, 2026.

Existingdescribed as
PENELECzone
115 kVkV as printed
4mentions

Also printed as: Garman Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Spangler Substation
PN-2024-003 · s3747.1
Not printed $14.2M 7/12/2027 Not printed 2026-10-06
TEAC
Garman Substation 115 kV Breaker B3, PA
PN-2026-008
Not printed Not printed Not printed Not printed 2026-06-16
SRRTEP Mid-Atlantic

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Penelec Local Plan Submission of Supplemental Projects for 2026 p. 17
Spangler Substation “At Garman: § Replace line relaying and substation conductor”
115 kV
2026-10-01* SRRTEP Mid-Atlantic
Penelec local plan submission for 2026 RTEP p. 17
Spangler Substation “At Garman: ▪ Replace line relaying and substation conductor”
2026-06-16 SRRTEP Mid-Atlantic
Item 04 - Penelec Supplemental Projects p. 7
Garman Substation 115 kV Breaker B3, PA “The existing B3 115 kV breaker at Garman Substation is 59 years old”
115 kV
2025-09-18 SRRTEP Mid-Atlantic
Item 05 - PENELEC Supplemental Projects p. 8
Spangler Substation “Replace line relaying and substation conductor”
115 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.