Rock Springs

Named in 1 PJM planning document for 2 projects, on June 17, 2026.

Not stateddescribed as
AMPTzone
—kV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
New Customer Service
AMPT 2026-010
Not printed Not printed Not printed 150 MW 2026-06-17
SRRTEP Western
New Customer Service
AMPT 2026-011
Not printed Not printed Not printed 170 MW 2026-06-17
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2026-06-17 SRRTEP Western
Item 01 - AMPT Supplemental Projects p. 5
New Customer Service No role wording
2026-06-17 SRRTEP Western
Item 01 - AMPT Supplemental Projects p. 6
New Customer Service No role wording