Sea Bright SW

Named in 1 PJM planning document for 1 project, on June 16, 2026.

Not stateddescribed as
JCPLzone
34.5 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Highlands-Long Branch 34.5 kV K89 Line Rebuild, NJ
JCPL-2019-025
Conceptual $28.27M 03/11/2030 Not printed 2026-06-16
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named HIGHLANDS; LONG BRANCH; MONMOUTH BEACH; SANDY HOOK; SANDY HOOK SW; SEA BRIGHT; SEA BRIGHT SW → HIGHLANDS; LONG BRANCH; SANDY HOOK; SEA BRIGHT 2026-06-16 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-06-16 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 12
Highlands-Long Branch 34.5 kV K89 Line Rebuild, NJ No role wording
34.5 kV