Substation Scout

Mudel

Named in 1 PJM planning document for 1 project, on June 2, 2026.

Newdescribed as
DOMzone
230 kVkV as printed
1mentions

Described as new: “new substation (Mudel)” — source, page 3

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2026-0025
Not printed Not printed 12/30/2029 300 MW 2026-06-02
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-06-02 TEAC
Item 11 - DOM Supplemental Projects p. 3
Dominion Transmission Zone: Supplemental Customer Load Request “new substation (Mudel)”
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.