Substation Scout

Ridgway

Named in 5 PJM planning documents for 3 projects, from October 8, 2024 to October 16, 2026.

Existingdescribed as
APSzone
138 kVkV as printed
5mentions

Also printed as: Ridgway Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Misoperation Relay Projects
APS-2024-008, APS-2024-011, APS-2024-013, APS-2024-015, APS-2024-016, APS-2024-024, APS-2024-030 to APS-2024-034 · s3470.1, s3471.1, s3472.1, s3473.1, s3474.1, s3475.1, s3476.1, s3477.1, s3478.1, s3479.1, s3480.1
Not printed Not printed Not printed Not printed 2024-10-08
TEAC
Elko Substation
APS-2024-037, PN-2024-015
Conceptual $44.66 M 12/13/2030 Not printed 2026-10-06
TEAC
Burma - Ridgway 138 kV Line
APS-2026-007
Conceptual $24.55 M 06/22/2029 Not printed 2026-10-16
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named ANTIETAM; BEDINGTON; BELMONT; BETHELBORO; CARNEGIE; CHARLEROI; DONEGAL; E HAGERSTOWN; EAST HAGERSTOWN; EDGELAWN; HAMPSHIRE; IRON BRIDGE; MARLOWE; PAPER CITY; RENO TAP; RIDGELEY; RIDGWAY; TIDD; TRISSLER; WEIRTON; YUKON → ANTIETAM; BETHELBORO; CHARLEROI; EAST HAGERSTOWN; PAPER CITY; RIDGWAY; YUKON 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 20
Burma - Ridgway 138 kV Line “At Ridgway Substation: Upgrade substation conductor, and revise relay settings.”
138 kV
2026-10-06 TEAC
Item 07 - APS Supplemental Projects - Presentation p. 7
Elko Substation “At Ridgway Substation: Replace 138 kV circuit breaker”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 117
Misoperation Relay Projects “At Ridgway, replace circuit breaker, disconnect switches, line trap and relaying”
138 kV
2026-06-17 SRRTEP Western
Item 03 - APS Supplemental Projects p. 3
Burma - Ridgway 138 kV Line No role wording
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 117
Misoperation Relay Projects “At Ridgway, replace circuit breaker, disconnect switches, line trap and relaying”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this