Substation Scout

Taneytown No. 1 Substation

Named in 1 PJM planning document for 1 project, on June 17, 2026.

Existingdescribed as
APSzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
New Customer Request
APS-2026-021
Not printed Not printed 12/30/2028 25 MW 2026-06-17
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2026-06-17 SRRTEP Western
Item 03 - APS Supplemental Projects p. 6
New Customer Request “near the existing Taneytown No. 1 Substation”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this