Substation Scout

Taneytown No.1 Substation

Named in 2 PJM planning documents for 1 project, from June 16, 2026 to September 17, 2026.

Existingdescribed as
METEDzone
—kV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Germantown Substation Customer Connection
ME-2026-007
Conceptual $130,000 01/31/2029 25 MW 2026-09-17
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 12/30/2028 → 01/31/2029 2026-06-16 2026-09-17
Substations named TANEYTOWN NO 1 → GERMANTOWN; TANEYTOWN NO 1 2026-06-16 2026-09-17

Every mention

DateDocumentProjectWhat the document says about it
2026-09-17 SRRTEP Mid-Atlantic
Item 02 - MetEd Supplemental Projects p. 5
Germantown Substation Customer Connection “near the existing Taneytown No.1 Substation”
2026-06-16 SRRTEP Mid-Atlantic
Item 03 - MetEd Supplemental Projects p. 5
Germantown Substation Customer Connection “near the existing Taneytown No.1 Substation”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.