Named in 1 PJM planning document for 1 project, on June 17, 2026.

Existingdescribed as
APSzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
New Customer Request
APS-2026-016
Not printed Not printed 04/06/2027 2 MW 2026-06-17
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2026-06-17 SRRTEP Western
Item 03 - APS Supplemental Projects p. 5
New Customer Request “approximately 1.4 miles from Sand Fork Substation”