Stephenson

Named in 3 PJM planning documents for 3 projects, from October 8, 2025 to June 17, 2026.

Not stateddescribed as
APSzone
138 kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
McCanns Rd 138 kV Switching Station
b4001.1
Not printed $23.87 M 6/1/2030 Not printed 2025-11-04
TEAC
Misoperation Relay Projects
APS-2026-029
Not printed Not printed Not printed Not printed 2026-06-17
SRRTEP Western
McCanns Rd 138 kV Switching Station
2025-W1-631
Not printed $23.87 M 6/1/2030 Not printed 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-06-17 SRRTEP Western
Item 03 - APS Supplemental Projects p. 10
Misoperation Relay Projects No role wording
138 kV
2025-11-04 TEAC
Item 14 - Reliability Analysis Update p. 9
McCanns Rd 138 kV Switching Station No role wording
138 kV
2025-10-08 TEAC
Item 13 - Reliability Analysis Update p. 8
McCanns Rd 138 kV Switching Station No role wording
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.