Named in 6 PJM planning documents for 7 projects, from October 8, 2024 to September 18, 2026.

Existingdescribed as
APSzone
138 kVkV as printed
8mentions

Also printed as: Ridgeley Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Misoperation Relay Projects
APS-2023-023, APS-2023-024, APS-2023-025
Not printed $3.2 M 11/17/2023 Not printed 2026-09-08*
SRRTEP Western
Misoperation Relay Projects
APS-2023-025 · s3102.1
Not printed $4.2 M 04/26/2024 Not printed 2024-10-08
TEAC
Misoperation Relay Projects
APS-2024-008, APS-2024-011, APS-2024-013, APS-2024-015, APS-2024-016, APS-2024-024, APS-2024-030 to APS-2024-034 · s3470.1, s3471.1, s3472.1, s3473.1, s3474.1, s3475.1, s3476.1, s3477.1, s3478.1, s3479.1, s3480.1
Not printed Not printed Not printed Not printed 2024-10-08
TEAC
Misoperation Relay Projects
APS-2024-016, APS-2024-024, APS-2024-030, APS-2024-031 · s3474.1, s3475.1, s3476.1, s3477.1
Not printed Not printed Not printed Not printed 2026-09-08*
SRRTEP Western
Finzel - Ridgeley 138 kV line
APS-2025-014
Conceptual $3.72 M 12/31/2030 Not printed 2026-09-18
SRRTEP Western
Hampshire - Ridgeley 138 kV Line
APS-2026-011
Not printed Not printed Not printed Not printed 2026-04-15
SRRTEP Western
Misoperation Relay Projects
APS-2026-027
Not printed Not printed Not printed Not printed 2026-06-17
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named PARKERSBURG; TRISSLER → GARRETT; GUILFORD; PARKERSBURG; REID; RIDGELEY; TRISSLER 2024-10-08 Not reported
Substations named ANTIETAM; BEDINGTON; BELMONT; BETHELBORO; CARNEGIE; CHARLEROI; DONEGAL; E HAGERSTOWN; EAST HAGERSTOWN; EDGELAWN; HAMPSHIRE; IRON BRIDGE; MARLOWE; PAPER CITY; RENO TAP; RIDGELEY; RIDGWAY; TIDD; TRISSLER; WEIRTON; YUKON → ANTIETAM; BETHELBORO; CHARLEROI; EAST HAGERSTOWN; PAPER CITY; RIDGWAY; YUKON 2024-10-08 Not reported
Substations named FINZEL; FROSTBURG; RIDGELEY → FINZEL; FROSTBURG NO 1; RIDGELEY 2025-04-11 2026-09-18

Every mention

DateDocumentProjectWhat the document says about it
2026-09-18 SRRTEP Western
Item 01 - APS Supplemental Projects p. 15
Finzel - Ridgeley 138 kV line “At Ridgeley Substation: replace circuit breaker, substation conductors, wave trap, CVT and relaying”
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 118
Misoperation Relay Projects “At Ridgeley, replace circuit breaker, disconnect switches, line trap, substation conductor and relaying”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 41
Misoperation Relay Projects “At Ridgeley Substation, replace wave trap, disconnect switches, substation conductor, & relaying”
138 kV
2026-06-17 SRRTEP Western
Item 03 - APS Supplemental Projects p. 9
Misoperation Relay Projects No role wording
138 kV
2026-04-15 SRRTEP Western
Item 02 - APS Supplemental Project p. 6
Hampshire - Ridgeley 138 kV Line No role wording
138 kV
2025-04-11 SRRTEP Western
Item 06 - APS Supplemental Project p. 4
Finzel - Ridgeley 138 kV line No role wording
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 118
Misoperation Relay Projects “At Ridgeley, replace circuit breaker, disconnect switches, line trap, substation conductor and relaying”
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 41
Misoperation Relay Projects “At Ridgeley Substation, replace wave trap, disconnect switches, substation conductor, & relaying”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.