Substation Scout

French Creek

Named in 8 PJM planning documents for 5 projects, from October 8, 2024 to October 16, 2026.

Existingdescribed as
APSzone
138 kVkV as printed
9mentions

Also printed as: French Creek Substation · French Creek 138 kV Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Misoperation Relay Project
APS-2021-007
Not printed Not printed Not printed Not printed 2024-10-08
TEAC
Misoperation Relay Project
APS-2021-009
Not printed Not printed Not printed Not printed 2024-10-08
TEAC
Misoperation Relay Projects
APS-2024-098 to 105, APS-2024-111 to 114, APS-2024-116, APS-2024-118
Not printed Not printed Not printed Not printed 2024-12-13
SRRTEP Western
Misoperation Relay Projects
APS-2024-114 · s3642.1, s3642.2
Not printed $7.1 M 03/30/2029 Not printed 2025-10-08
TEAC
French Creek - Sutton 138 kV Line
APS-2026-012
Conceptual $119.57 M 05/06/2033 Not printed 2026-10-16
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named BELMONT; FRENCH CREEK; JOHNS JCT; OAK GROVE; PARKERSBURG; PICKENS; TRISSLER → BELMONT; FRENCH CREEK; OAK GROVE; PARKERSBURG; PICKENS; TRISSLER 2024-10-08 Not reported
Substations named FRENCH CREEK; HEATERS TAP; SUTTON → FRENCH CREEK; SUTTON 2026-04-15 2026-10-16

Every mention

DateDocumentProjectWhat the document says about it
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 14
French Creek - Sutton 138 kV Line “At French Creek Substation: Remove wave trap, line turner and coax, and install fiber.”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 79
Misoperation Relay Project “French Creek 138 kV Substation – Replace substation conductor, circuit breaker, and wave trap”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2025 RTEP p. 27
Misoperation Relay Projects “French Creek Substation: At French Creek, replace circuit breaker”
138 kV
2026-04-15 SRRTEP Western
Item 02 - APS Supplemental Project p. 8
French Creek - Sutton 138 kV Line No role wording
138 kV
2025-10-08 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2025 p. 27
Misoperation Relay Projects “At French Creek, replace circuit breaker, disconnect switch”
138 kV
2025-02-14 SRRTEP Western
Item 04 - APS Supplemental Projects p. 7
Misoperation Relay Projects “At French Creek, replace circuit breaker, disconnect switch, substation conductor, wave trap, line turner and coax, and relaying.”
138 kV
2024-12-13 SRRTEP Western
Item 15 - APS Supplemental Project p. 6
Misoperation Relay Projects No role wording
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 78
Misoperation Relay Project No role wording
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 79
Misoperation Relay Project “French Creek 138 kV Substation – Replace substation conductor, circuit breaker, and wave trap”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.