Substation Scout

Rosehill

Named in 4 PJM planning documents for 1 project, from February 14, 2025 to October 8, 2025.

Not stateddescribed as
COMEDzone
138 kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Devon Hardening
ComEd-2025-003 · s3726.1
Engineering $ 18.9 M 12/31/2026 Not printed 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ComEd local plan submission of the supplemental projects for 2025 RTEP p. 28
Devon Hardening No role wording
138 kV
2025-10-08 TEAC
Informational Only - ComEd Local Plan Submission of the Supplemental Projects for 2025 p. 28
Devon Hardening No role wording
138 kV
2025-03-14 SRRTEP Western
Item 03 - ComEd Supplemental Projects p. 5
Devon Hardening No role wording
138 kV
2025-02-14 SRRTEP Western
Item 03 - ComEd Supplemental Projects p. 3
Devon Hardening No role wording
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this