Riverside

Named in 1 PJM planning document for 1 project, on February 4, 2025.

Not stateddescribed as
PJM system-widezone
230 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Brandon Shores Deactivation Project Updates: Summary of Cost Changes
b3780.1
Not printed 1513.96 12/31/2028 Not printed 2025-02-04
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
738.83 → 1513.96 2025-02-04 2025-02-04

Every mention

DateDocumentProjectWhat the document says about it
2025-02-04 TEAC
Item 12 - Reliability Analysis Update p. 13
Brandon Shores Deactivation Project Updates: Summary of Cost Changes No role wording
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.