Duval

Named in 2 PJM planning documents for 1 project, from February 4, 2025 to October 8, 2025.

Newdescribed as
DOMzone
230kVkV as printed
2mentions

Described as new: “new substation (Duval)” — source, page 3

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Duval 230kV Delivery - DEV
DOM-2024-0031 · s3677
Engineering $30.0M Substation, $80M Transmission Lines 1/1/2028 76.9 MW 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named DUVAL; MIDLOTHIAN; WINTERPOCK → DUVAL; MIDLOTHIAN 2025-02-04 2025-10-08

Every mention

DateDocumentProjectWhat the document says about it
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 32
Duval 230kV Delivery - DEV “new substation (Duval)”
230kV
2025-02-04 TEAC
Item 11 - Dominion Supplemental Projects p. 3
Duval 230kV Delivery - DEV “new substation (Duval)”
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.