Substation Scout

Pine Hill

Named in 3 PJM planning documents for 1 project, from February 13, 2025 to October 8, 2025.

Existingdescribed as
ACEzone
69kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Pine Hill Substation
ACE-2024-003 · s3664.1
Conceptual $35.53 M 9/1/2029 Not printed 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $27.4 M → $35.53 M 2025-02-13 2025-10-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
ACE local plan submission for 2025 RTEP p. 2
Pine Hill Substation “Rebuild Pine Hill as a 7-position GIS breaker-and-a half substation.”
69kV
2025-10-08 TEAC
Informational Only - ACE Local Plan Submission of the Supplemental Projects for 2025 p. 2
Pine Hill Substation “The Pine Hill 69kV substation was installed in the 1960’s”
69kV
2025-02-13 SRRTEP Mid-Atlantic
Item 02 - ACE Supplemental Projects p. 3
Pine Hill Substation “Rebuild Pine Hill as a 7-position indoor GIS breaker-and-a-half substation”
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.